2016年11月25日星期五

Trailer Mounted Mud Control System for Workover Rig

Brightway designed and developed this Trailer Mounted Mud Control System for customer specially, Because of Large structure of mud solid control system and difficulty to transport, can not carry quickly. The Trailer Mounted Mud Control System designed and manufactured by Brightway for the customer of Iraq, transported to Tianjin port by 12 tractor-semitrailers. This Trailer Mounted Solids Control System adopt Trailer Mounted design and configure 4 phase solids control equipment and composed of six pull-type mud tanks and other tanks including fire control tank, waste water tank, diesel tank, water tank. The biggest processing capacity of system is 240m3 /h.


Trailer Mounted Mud Control System for Workover Rig


The Trailer Mounted Mud Control System can realize trailer transport directly without lift. It has strong maneuverability and can emergency to avoid conflict rapidly. Shortened the time to move and Reduce the cost. It can ensure that Mud preparation, aggravating, screening, realize smoothly in the process of 4000m drilling. In addition, This Trailer Mounted Mud Control System configure a fire control tank, composed of electric-drive fire pump and Diesel fire pump,can ensure safe under the condition of generator did not work. The whole Trailer Mounted Mud Control System of the high production standards, excellent production technology, is the first in the country.

According to the customer request and based on the actual environment, Brightway has completed well the production task of Trailer Mounted Mud Control System, Skid mounted Mud Control System at home and abroad. After many years of production experience accumulated, Brightway can design and manufacture different types of Trailer Mounted Mud Control System or Skid Mounted Mud Control System for different drilliing rig or workover rig. Welcome new and old customers to come to Brightway company to discuss cooperation.

2016年11月14日星期一

BWZCQ300 Vacuum Degasser - Brightway Solids

We know that the excellent vacuum degasser has very important function: get rid of harmful gas in drilling fluid; recover the proportion of mud; stable viscosity properties of mud; reduce the drilling cost.

Recently, Brightway one set BWZCQ300 vacuum degasser has sent to a drilling site. This vacuum degasser will be matching with drilling mud conrol system. According to the request of the customer, the BWZCQ300 vacuum degasser has been painted dark blue.



The accessories of vacuum degasser adopted the well-known brands at home and abroad. The capacity is up to 300m3/h. The degassing efficiency is 95% ~ 95%.

According to the different drilling depth and the customer requirment, Brightway can manufacture  different capacity vacuum degasser, such as BWZCQ240 (240m3/h),BWZCQ270(270m3/h),BWZCQ360(360m3/h).

http://www.solidscontrolsystem.com/product-item/vacuum-degasser/

2016年11月8日星期二

Brightway Shale Shaker Operation Video For Oil Drilling in Russia


Shale Shaker Video Information

Shale Shaker Model: BWZS103, Treatment
Capacity: 120 m3/h,
Job Site: Samara, Russia,
Project: 4000m Oil Drilling

This Shale Shaker Model is the Brightway  BWZS103 ( Oli morto and 3 pices shaker screes ) the Shale Shaker Capacity is 120 m3/h.

Know more about Brightway Shale Shaker information,please click here:  http://www.solidscontrolsystem.com/product-item/shale-shaker/

2016年11月2日星期三

Piling Slurry Treatment Schemes


Piling Slurry Treatment has always been a problem in engineering construction.In the process of piling, There will produce a lot of mud. the mud is suspension liquid contains a certain amount of fine clay particles, which has a certain viscosity and difficult to separation for a long time. Now how can we treatment these mud from piling?

Four Piling Slurry Treatment Schemes

1. Piling Mud Treatment Scheme of Sedimentation basin : On construction site, we can construct one sedimentation basin. First, we need to discharge sewage into sedimentation basin. Removing suspended solids, oil material and Neutralization processing, after detection to achieve discharge standard, we can discharge into the river.
2. Piling Slurry Treatment Scheme of Natural dehydration: In the process of drilling perfusion, we can use shaker screen to seprate small gravel, sand and other solid particles from pile mud. then discharge it into mud pit and sufficient to precipitate until the natural dehydration and solidification.
3. Piling Slurry Treatment Scheme of Flocculation Treatment: For waste mud water, we can add flocculants into it. Because the mud is suspension liquid contains a certain amount of fine clay particles, the macromolecule flocculant is a kind of water-soluble polymer,When mixed with mud water, it can destroy the stability of the slurry water in order to settlement of clay particles from the water condensed quickly.
4. Piling mud slurry equipment: This method is to use the special pile mud treatment equipment to separate the mud from slurry water. Such as piling mud centrifuge, piling mud dewatering machine, piling mud separator, piling mud curing equipment. The biggest advantages of this method is convenient and effort. Sludge treatment efficiency, more environmental protection.

Brightway Piling mud treatment equipment


Know more about Piling Slurry Treatment Schemes: http://www.solidscontrolsystem.com/slurry-treatment-plant/